Factsheet
- Offices: 2,000 m² GLA
Project duration
- First draft team meeting: 13 December 2016
- Environmental permit application; 27 January 2017
- Documents for tender issued: 17 February 2017
- Quotes received: 10 March 2017
- Agreement executing parties Strukton and Hoppenbrouwers: 24 March 2017
- Environment licence received: 27 March 2017
- First construction meeting: 10 April 2017
- Start of drilling piles: 08 June 2017
- Construction pit excavation: 12 June 2017
- Highest point: 17 August 2017
- Handover / Go-live: 15 December 2017
VB&T Activities
vb&t Projectmanagement has performed the total cost and project management for this project from the initiation phase through to the aftercare phase. The project included the following work activities for vb&t, amongst others:
- Plan development with external consultants
- Cost management
- Selection, pricing and contract formation
- Management during construction