“vb&t Projectmanagement excels particularly at fostering cooperation and connection between the client, property manager, advisory parties, executing parties, and not least, our tenants. This, combined with sound professional and market knowledge, makes vb&t Projectmanagement a very pleasant and reliable partner for us in making projects a success.”
Mr Rutsen, Technical Manager Syntrus Achmea
| Category | Office |
| Client | Syntrus Achmea Real Estate & Finance |
| Location | Nijmegen |
| Construction costs | £420,000 excl. VAT incl. installations |
| Architect: | Studio Y |
Project Description
This concerns the revitalisation of the entrance, common areas, office floors 3 and 4, and the sanitary facilities to create a modern office building with a contemporary and functional appearance.
Factsheet
- Starter
- Toilet facilities
- Communal areas
- Office floors 3/4
Project duration
- Start preparation phase 1 entrance and common areas: March 2013
- Completion phase 1: November 2013
- Start preparation phase 2, toilets and office floors 3 and 4: August 2016
- Completion of toilets and office floors 3 and 4, phase 2: January 2017
VB&T Activities
vb&t Projectmanagement carried out the complete cost and project management for this project, from the initiation phase through to the aftercare phase. The project included, among other things, the following activities:
- Drawing up the architectural work descriptions
- Plan development with external consultants
- Cost management
- Selection, pricing and contract formation
- Management and supervision during implementation