| Category | Social |
| Client | KempenPlus |
| Location | Bladel |
| Construction costs | To request |
| Architect: | FAAM BO2 Architects |
Project Description
The project consists of the expansion and revitalisation of the offices and business (production) areas of KempenPlus. The project is located at Raambrug 8 in Bladel. Staff accommodation and the continuity of KempenPlus' operations are central during the phased renovation so that business operations can continue as far as possible.
Factsheet
- Total gross floor area: 2,500
- Lead time: approx. 13 months
- Phase 1, procurement after summer 2020
Project duration
- Start planning: 2019
- Start realisation phase: Q3 2020
- Completion: Q4 2021
VB&T Activities
For this project, vb&t Project Management performs total cost and project management from the final design phase DO to the after-care phase. For vb&t, the project includes the following activities:
- Plan development with external consultants
- Construction team selection, pricing and contracting
- Cost management
- Construction supervision during execution
- Aftercare