MFC ‘De Mortel’, Gemert-Bakel

CategoryMFC
ClientGemert-Bakel Municipality
LocationGemert-Bakel municipality
Construction costs£4,800,000.00 excluding VAT
Architect:Optimum Local
Project Description

The project, located in the centre of De Mortel, comprises the construction of a new multi-purpose facility. The new build was tendered and realised using the Design Construct & Maintenance method. The project was tendered based on, among other things, a technical, spatial, and functional Programme of Requirements drawn up as well as possible (down to the detail). In addition, the score for this GPR building was set at a minimum of 8.0.

Factsheet
  • Primary school: 1,040 m² GFA
  • KDO / BSO: 190 m² GFA
  • Health centre: 200 m² GIA
  • Village Hall: 825 m² GIA
  • Sports hall: 650 m² GFA
Project duration
  • Design start: 2010
  • Start realisation phase: 3rd quarter 2012
  • Construction ready: end of Q2 2013
VB&T Activities

vb&t Projectmanagement is responsible for the total cost and project management for this project, from the definition phase through to the aftercare phase. The project included the following activities for vb&t, amongst others:

  • Feasibility study(ies)
  • Completing the Programme of Requirements
  • DCM contractor development plan
  • Cost management
  • Selection, pricing and contract formation
  • Management / supervision during implementation
  • Aftercare