Pathé De Kuip Dolby Cinema, Rotterdam

CategoryLeisure
ClientPathé Theatres B.V.
LocationRotterdam
Construction costsTo request
Architect:Dolby Cinema vs / Buroh
Project Description

The project involves the transformation of auditorium 9 at Pathé De Kuip into a Dolby Cinema auditorium. The transformation was carried out between September 2017 and November 2017 in collaboration with Dolby Cinema. The cinema remained in operation during this period.

Factsheet
  • Total number of seats: 445
  • Continuous operation cinema
  • Lead time of 12 weeks, construction start to completion
  • AVP entrance experience with 3 projectors
Project duration
  • Plan development and preparation: June 2017
  • Start of realisation phase dismantling: September 2017
  • Completion: November 2017
VB&T Activities

vb&t Projectmanagement carried out the total cost and project management for this project, from development through to the aftercare phase. The project included, among other things, the following activities:

  • Voortgezet Onderwijs/Directie Overleg planning met Dolby Cinema
  • Construction team plan elaboration UT
  • Selection, pricing and contract formation
  • Cost management
  • Management during construction

The order involved the complete transformation including furniture and Dolby Cinema.