Pathé Tuschinski Arthouse, Amsterdam

CategoryLeisure
ClientPathé Theatres B.V.
LocationAmsterdam
Construction costsTo request
Architect:Doka Concepts / Buroh
Project Description

The entire Tuschinski Arthouse (comprising three halls, the foyer, and restrooms) has been renovated in the style of the Tuschinski theatre. The halls are equipped with luxury seating, love seats, and the visuals and sound have been modernised. A cocktail and drinks bar has been realised in the foyer, allowing visitors to experience a complete day or evening out.

Factsheet
  • Total number of seats: 230
  • Total m²: 794
  • Continuous operation cinema
  • Lead time (start of construction to handover) of just 11 weeks
Project duration
  • Start of plan development: November 2019
  • Start implementation phase: January 2020
  • Completion: March 2020
VB&T Activities

vb&t Projectmanagement has performed the total cost and project management for this project from the initiation phase through to the aftercare phase. The project included the following work activities for vb&t, amongst others:

  • Plant development VO / DO
  • Cost management
  • Selection, pricing, and contract formation for a construction team
  • Management during construction