The project (located at Vijfkamplaan 5 in Eindhoven) consists of the new construction of a sports and gymnastics complex. vb&t Projectmanagement has managed this project from the planning stage through to execution and aftercare. The sports complex comprises a multi-functional sports hall and a gymnastics hall. In addition, catering and changing facilities are integrated into the complex.

Factsheet
  • Multifunctional sports hall: 2,350 m² GFA
  • Sports hall: 1,350 m² gross floor area
Project duration
  • Start of plan development: January 2006
  • Completion: February 2007
VB&T Activities

vb&t Projectmanagement carried out the total cost and project management from the initiation phase through to the aftercare phase. The project included, among other things, the following activities:

  • Feasibility study(ies)
  • Prepare Programme of Requirements
  • Plan development with external consultants
  • Cost management
  • Selection, pricing and contract formation
  • Management during construction
  • Aftercare