| Category | Sport |
| Client | Eindhoven Municipality |
| Location | Eindhoven |
| Construction costs | €5,400,000 (excluding VAT, including installations) |
| Architect: | Spierings & Swart Architects |
Project Description
The project (located at Vijfkamplaan 5 in Eindhoven) consists of the new construction of a sports and gymnastics complex. vb&t Projectmanagement has managed this project from the planning stage through to execution and aftercare. The sports complex comprises a multi-functional sports hall and a gymnastics hall. In addition, catering and changing facilities are integrated into the complex.
Factsheet
- Multifunctional sports hall: 2,350 m² GFA
- Sports hall: 1,350 m² gross floor area
Project duration
- Start of plan development: January 2006
- Completion: February 2007
VB&T Activities
vb&t Projectmanagement carried out the total cost and project management from the initiation phase through to the aftercare phase. The project included, among other things, the following activities:
- Feasibility study(ies)
- Prepare Programme of Requirements
- Plan development with external consultants
- Cost management
- Selection, pricing and contract formation
- Management during construction
- Aftercare