Pathé De Kuip, Rotterdam

CategoryLeisure
ClientPathé Theatres B.V.
LocationRotterdam
Construction costsTo request
Architect:Labour
Project Description

The project involves the complete renovation of the 13 regular auditoriums at Pathé De Kuip, to be carried out between February and July 2025. The auditoriums are being fully refurbished. Throughout the renovation, the cinema remained open and operational, with no disruption to the regular business operations.

The project includes 1,660 Relax Seats and was carried out while the cinema remained open. The renovation was completed within a turnaround time of 20 weeks, from the start of construction through to handover.

Start plan development
Start implementation phaseFebruary 2025
CompletionJuly 2025
VB&T Activities

vb&t Projectmanagement handled the total cost and construction management for this project, from the development phase through to the aftercare phase. For vb&t, the project included, among other things, the following activities:

  • Development plan for secondary education/vocational education
  • Cost management
  • Selection, pricing and contract formation
  • Management during construction