| Category | Industry, Office |
| Client | Langfruit Fruit & Vegetables |
| Location | Venlo |
| Construction costs | £5,600,000 (excluding VAT, including installations) |
| Architect: | Quant Architecture |
Project Description
The project located at Freshpark Venlo comprises the new construction of the head office and the logistics hall for Langfruit Fruit & Vegetables. The building includes a climate-controlled (8 – 18 °C) logistics hall with nine cold stores (0 – 12 °C) and offices.
Factsheet
- Office: 700 m2 BVO
- Logistics hall: 10,000 m²2 BVO
- 20 load docks
- 9 cold rooms
- Heat recovery from cooling hall for office
Project duration
- Project start: December 2004
- Start of construction: September 2006
- Delivery: September 2007
VB&T Activities
vb&t Projectmanagement carried out the complete cost and project management for this project, from the initiation phase through to the aftercare phase. The project included, among other things, the following activities:
- Feasibility study(ies)
- Prepare Programme of Requirements
- Plan development with external consultants and contractor
- Cost management
- Selection, pricing and contract formation
- Project management during realisation including procurement and coordination for interior design and landscape design
- Aftercare