| Category | MFC, Sport |
| Client | Municipality of Cuijk |
| Location | St. Agatha (municipality of Cuijk) |
| Construction costs | £1,600,000 excluding VAT |
| Architect: | Leenders Architects |
Project Description
The development and realisation of a new multi-purpose facility for the municipality of Cuijk, named MFC De Agaat. This facility houses several different functions, including a sports hall, catering/canteen, and various rooms for use by sports clubs, a day nursery, youth care, a brass band, etc. The new construction was tendered and realised using the Design Construct & Maintenance method, and the score for GPR Building was set at a minimum of 7.8. In addition to the new construction, the outdoor area, including the construction of sports fields, was also redeveloped.
Factsheet
- 1,300 m² GFA (building)
Project duration
- Design start: April 2010
- Start realisation phase: April 2011
- Construction ready: end of the first quarter of 2012
- Start outdoor area: July 2012
- Outdoor area ready: September 2012
VB&T Activities
vb&t Projectmanagement carried out comprehensive cost and project management for this project, from the definition phase through to post-project review. The project included, among other things, the following activities:
- Feasibility study(ies)
- Completing the Programme of Requirements
- DCM contractor development plan
- Cost management
- Selection, pricing and contract formation
- Project management / supervision during realisation
- Aftercare