Pathé Dolby Cinema, Scheveningen

CategoryLeisure
ClientPathé Theatres B.V.
LocationScheveningen
Construction costsTo request
Architect:Dolby Cinema vs / Buroh
Project Description

The project involves the transformation of Auditorium 4 at Pathé Scheveningen into a Dolby Cinema auditorium. The transformation was carried out between April 2018 and 9 July 2018 in collaboration with Dolby Cinema. The cinema remained operational during this period.

Factsheet
  • Total number of seats: 281
  • Continuous operation cinema
  • Lead time of 12 weeks, construction start to completion
  • AVP entrance experience with 4 projectors
  • The assignment concerned the complete transformation including furniture and Dolby Cinema.
Project duration
  • Plan development and preparation: March 2018
  • Start realisation phase demolition: 16 April 2018
  • Delivery: 9 July 2018
VB&T Activities

vb&t Projectmanagement carried out the total cost and project management for this project, from development through to the aftercare phase. The project included, among other things, the following activities:

  • Voortgezet Onderwijs/Directie Overleg planning met Dolby Cinema
  • Construction team plan elaboration UT
  • Selection, pricing and contract formation
  • Cost management
  • Management during construction