Pathé Tuschinski, Amsterdam

CategoryLeisure
ClientPathé Theatres B.V.
LocationAmsterdam
Construction costsTo request
Architect:Rappange & Partners Architects B.V. / Artist's Studio: Liesbeth Stinissen
Project Description

The project involves the renovation of halls 2 and 3 of the monumental Pathé Tuschinski, carried out between July and September 2019. The halls were completely refurbished and restored to the theatre's original style, with the walls and ceiling decorated with reconstructed paintings executed by an artist. Throughout the renovation, the cinema remained open and operational, without any disruption to regular business.

The project involved 173 chairs and was carried out while the cinema remained in continuous operation. The renovation was completed within a turnaround time of 11 weeks, from the start of construction to handover.

Start plan developmentJanuary 2019
Start implementation phaseJuly 2019
CompletionSeptember 2019
VB&T Activities

vb&t Projectmanagement handled the total cost and construction management for this project, from the development phase through to the aftercare phase. For vb&t, the project included, among other things, the following activities:

  • Development plan for secondary education/vocational education
  • Cost management
  • Selection, pricing and contract formation
  • Management during construction