| Category | Office, Care |
| Client | Vivent Foundation |
| Location | Rosmalen |
| Construction costs | €900,000 excl. VAT |
| Architect: | Area Occupier Solutions |
Project Description
Realisation of new office accommodation for Vivent following the sale of existing offices. Part of the interior has made use of the reuse of materials from the old office interior.
In just 7 months, the entire planning, development, and implementation phases have been completed. By establishing the fundamental principles early on with the maintenance installers and the selected contractor, we have been able to realise this project within this very short timeframe in a heated market.
Factsheet
- Circa 850 sq m GFA
- Fully equipped with LED lighting
- Reuse of materials in interiors
- Renovation of main building basement
Project duration
- Project planning: May 2018
- Start implementation phase: September 2018
- Delivery: December 2018
VB&T Activities
vb&t Projectmanagement has performed the total cost and project management for this project from the initiation phase through to the aftercare phase. The project included the following work activities for vb&t, amongst others:
- Plan development with external consultants
- Cost management
- Selection, pricing and contract formation
- Construction supervision during execution
- Aftercare