TrainMore, The Hague

CategoryLeisure, Sport
ClientTrainMore
LocationThe Hague
Construction costs€630,000 ex. VAT incl. installations and fixed furnishings
Architect:VENS Architects
Project Description

Commissioned by TrainMore, the development of the new TrainMore branch in The Hague began in 2012. The monumental building at Dagelijkse Groenmarkt 19 has been completely renovated into a gym with changing rooms, a lobby, a bar and rooms for a dietician and physiotherapist, while retaining the building's character.

Factsheet
  • Share TrainMore approx. 2,100 m² GFA
  • Aerobics: approx. 200 m²
  • Spinning: approximately 120 m²
  • (Cardio) Fitness: approximately 650 m²
  • Physiotherapy, dietitian, and solarium: approximately 90 m²
Project duration
  • Start design process: July 2012
  • Build: February 2013
  • Completion: May 2013
VB&T Activities

vb&t Projectmanagement provided total cost and project management for this project, from the initiation phase through to the aftercare phase. The project involved the following activities:

  • Prepare Programme of Requirements
  • Project development with design team
  • Cost management
  • Selection, pricing and contract formation
  • Management during construction

Additionally, vb&t has handled the procurement and coordination for the bespoke carpentry and furniture.