Project Description

The project (located at Vlagheide 2 in Schijndel) consists of the new construction of a production hall, tank and wash bay, the expansion of the head office, and the restoration of the existing sustainability hall and office building.

Factsheet
  • New office build: 120 m2 BVO
  • Office renovation: 400 m²2 BVO
  • New build: 1000 m²2 BVO
  • Hall renovation: 2,000 m²2 BVO
  • Ground renovation: 1,100 m2 BVO
Project duration
  • Plan development and preparation: September 2010
  • Project start: December 2010
  • Project end: July 2011
VB&T Activities

vb&t Projectmanagement has carried out total cost and project management from the preliminary design phase through to the aftercare phase.