The Grid Office Building, Utrecht

CategoryOffice
ClientAPF pension fund foundation
LocationUtrecht
Construction costsTo request
Architect:Ditt. Officemakers
Project Description

The office building The Grid at Euclideslaan 251-253 in Utrecht is being renovated. The renovation involves adapting the façade and window frames to give the building a modern look. The facade on the ground floor will also be adapted to create more transparency. The parking deck will be fully repaired and coated. The sanitary facilities and shared areas will be modernised. The upper floors will be returned to shell and made rental-ready. The design phase was completed by the end of September 2020. The implementation phase started in October 2020.

Factsheet
  • Total area: 6000 m2
  • Lead time: 12 months
  • 8 storeys
Project duration
  • Start of plan development: April 2020
  • Start implementation phase: October 2020
  • Completion: April 2021
VB&T Activities

vb&t Projectmanagement has performed the total cost and project management for this project from the initiation phase through to the aftercare phase. The project included the following work activities for vb&t, amongst others:

  • Plan development with external consultants
  • Cost management
  • Design & Build contracting
  • Construction supervision during execution
  • Aftercare